All flagging, permits, TMPs for all deliveries should always be excluded by all the trades. This piece may be helpful in your future interviews with clients and potential clients.
Why we exclude flagging of deliveries:
It’s a blank cheque – When we’re bidding a project, we don’t know what arrangements the client is going to make for staging and deliveries. Often the GC or CM don’t know until they’ve met with the City. Will there be a full lane closure? Partial parking spaces only? Arrangements for adjacent properties? Will wires be moved or protected? Will lamp-posts or trees be permanently or temporarily removed? Will the City impose time restrictions on any closures? What will the City’s requirements be for any closures? This means the number of Traffic Control personnel, and the times they are required, are not quantifiable. Unless the parameters are clearly defined, agreeing to provide flagging for deliveries could cost tens of thousands of dollars or even hundreds of thousands.
It’s not economical – If every trade on the site is required to flag their deliveries, there could be up to 20 people involved in the process. If each trade allows for the cost of this, it would far exceed the cost of the GM or CM assigning one full-time person to handle pedestrian and vehicular traffic.
It’s not efficient – If each trade is required to have a flagperson, then the GC or CM has to police each one. Scrutinizing the flagging of up to 20 trades or more becomes a full-time job in itself. And the GC/CM has to ensure the process is done according to arrangements made with authorities such as the City, Coast Mountain Bus, WorkSafeBC, neighbours and others. For the effort to manage a group of likely unqualified flaggers, it’s more efficient to assign one qualified person to the task. And if a trade hires a flagger (say Labour Unlimited), will they be there when the delivery arrives? A full-time flag person solves all these issues and provides a facility for handling late or early deliveries.
It’s unsafe – When each trade is tasked with flagging their own deliveries, it’s likely that a good number of them will not be familiar with the processes and the hazards for the particular site. Some won’t have the appropriate PPE, or even the traffic paddles, cones and signs that the process requires. It becomes a gong show because trade personnel will be motivated to achieve the delivery, with flagging as a secondary concern.
It can disrupt trade work onsite – When a trade is obliged to provide one of their crew to flag a delivery, that person’s work is disrupted and their work area is left unattended – possibly without assessing any “unattended” hazards.
It can increase friction between personnel – Flagging of deliveries is largely a function of public safety. This is a priority for site CSO’s. Dogging trades that struggle with their flagging duties puts a strain on those trades and the CSO. Having the flag person and CSO both work for the GC or CM, under the direction of the Site Superintendent, eliminates this potential for friction between personnel.
It’s bad for public relations – The authorities – especially the City that issues the permits for street use – will appreciate a site where vehicular and pedestrian traffic are handled professionally and properly. Using a grab-bag of various personnel from various trades will not achieve the same standard as having a knowledgeable person assigned specifically to handling traffic during deliveries.
It’s good Risk Management – If and when there is an incident relating to the flagging of deliveries, the answer to the “What did you do to manage this hazard?” has a credible answer: “We assigned a full-time qualified flag person to minimize risk.” Saying you handed the responsibility for flagging to each trade only begs the question: “OK, and what did you do to supervise the trades?” As noted above, that in itself is a full-time job.
| S | M | T | W | T | F | S |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | ||
| 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| 13 | 14 | 15 | 16 | 17 | 18 | 19 |
| 20 | 21 | 22 | 23 | 24 | 25 | 26 |
| 27 | 28 | 29 | 30 | 31 | ||

2 Comments. Leave new
I could not agree more with your take on the flagging, all the reasons given are valid.
We never agree to do the flagging unless we supply all the material including concrete and rebar.
Good article. This gives some good ammunition in negotiation as this is a scope item that we are constantly dealing with. I often get the feed back from the GC’s that everyone includes their own flagging. We don’t!